Distributed-generator power-generation-amount estimation apparatus and method
Granted 9 Jun 2020 · no office action yet
Assignee: Hitachi, Ltd.
Law firm: Law firm · Log in to unlock
Attorney: Attorney · Log in to unlock
Inventors: Masahiro Adachi, Hirotaka Takahashi, Katsuhiro Matsuda · Examiner: Manuel L Barbee · AU 2864 · TC 2800
Life of the application
8 dated eventsAbstract
A distributed-generator power-generation-amount estimation apparatus and method capable of more accurately and easily estimating output by reflecting a power factor are disclosed. The apparatus estimates a power generation amount of a distributed generator interconnected to an electric power system from active power and reactive power measured at regular intervals by measurement means, the apparatus including power-factor estimation means for estimating, as a ratio of a time change amount of the active power and the reactive power, a power factor of the distributed generator interconnected to a demand side of the electric power system, distributed-generator power-generation-amount estimation means for having, from active power and reactive power measured at a time of no power when the distributed generator interconnected to the electric power system is not generating power, a first characteristic line representing a load characteristic on a coordinate plane based on active power and reactive power, a second characteristic line representing a distributed-generator characteristic on the coordinate plane, and estimating the difference between the active power and the reactive power at an intersection point of the first characteristic line and the second characteristic line, and the measured active power and the measured reactive power as the power generation amount of the distributed generator, and output means for outputting power-generation-amount estimation information on the distributed generator estimated by the distributed-generator power-generation-amount estimation means.
Description
12 parts›TECHNICAL FIELD
The present invention relates to a distributed-generator power-generation-amount estimation apparatus and method.
›BACKGROUND ART
In recent years, the interconnection amount of distributed generators DG including photovoltaic power generation to an electric power system is increasing for the purpose of protecting the global environment. On the other hand, a distributed generator DG has a risk of sudden change in power generation due to weather such as clouds and wind. Power companies have a need to know the output of the distributed generator DG frequently, such as at intervals of several seconds, and precisely in order to stably supply electric power.
As a conventional technique, Non-Patent Document 1 discloses a technique for estimating output of a distributed generator DG. The document discloses a method for estimating output of a distributed generator DG by using a power-factor method.
In the estimation of the output of a distributed generator DG by the power factor method, by assuming a coordinate plane in which the abscissa is active power P and the ordinate is reactive power Q, putting plots on the PQ coordinate plane according to the active power P and reactive power Q measured in units of banks of a substation or the like while the distributed generator DG is stopped, and performing, for example, linear approximation processing based on these plots, a load characteristic of the electric power system is specified in advance. This load characteristic is a characteristic when there is no distributed generator in the electric power system.
Next, plots are put on the above active power/reactive power coordinate plane according to real time active power P and reactive power Q (measured, for example, at 10-second intervals) measured in units of banks of the substation or the like. Supposing that the distributed generator DG operates at a power factor of 1, the distributed generator DG outputs only active power. Therefore, when it is assuming that the real-time active power measurement value is P 1 and the real-time reactive power measurement value is Q 1 , the output of the distributed generator DG is calculated by Formula (1).
[Mathematical Formula 1]
output of distributed generator DG =active power P 0 obtained from load characteristic when reactive power is Q 1−measured real time active power P 1 (1)
The advantage of the power-factor method is that it is possible to calculate the output of the distributed generator DG at that point each time active power and reactive power is measured in units of banks of a substation or the like, and then it is possible to estimate the output of the distributed generator DG frequently.
Measurement of active power and reactive power in units of banks of a substation means that active power and reactive power in an electric-power supplying target area connected via a feeder (distribution line) to the bank. For this reason, the estimation of the power generation amount means to estimate the power generation amount of the distributed generator in units of areas.
›CITATION LIST
Non Patent Literature
NPL 1: Matsuda et al., “Bunsangata Dengen no Untenjoukyou Suiteisyuhou no Teian” IEEJ Transactions on Power and Energy, Vol. 130 No. 6 Pages 593-602 (2010)
›SUMMARY OF INVENTION
Technical Problem
In the method disclosed in Non-Patent Document 1, since the power generation amount of the distributed generator DG is estimated based on the assumption that the power factor of the distributed generator DG is 1, there is a problem that an error is included in the power-generation-amount estimation value of the distributed generator DG in the case where the distributed generator DG is operated at a power factor other than 1.
On the other hand, since it is generally assumed that a power factor of a distributed generator DG is other than 1, it is desirable to calculate the power factor of the distributed generator DG and use it for estimating the output of the distributed generator DG.
In view of the above, the present invention is to provide a distributed-generator power-generation-amount estimation apparatus and method that can estimate output more precisely and easily by reflecting a power factor.
Solution to Problem
In order to solve the above problem, a configuration described in, for example, claims is adopted. The present invention includes a plurality of means for solving the above problem, and is, for example, a distributed-generator power-generation-amount estimation apparatus that estimates, from active power and reactive power measured at regular intervals by measurement means installed on an electric power system, a power generation amount of a distributed generator interconnected the an electric power system, the distributed-generator power-generation-amount estimation apparatus including power-factor estimation means for estimating, as a ratio of a time change amount of the active power and the reactive power, a power factor of the distributed generator interconnected to a demand side of the electric power system from a measurement point by the measurement means, distributed-generator power-generation-amount estimation means for having, from active power and reactive power measured at a time of no power when the distributed generator interconnected to the electric power system is not generating power, a first characteristic line representing a load characteristic on a coordinate plane based on active power and reactive power, determining, from the measured active power, the measured reactive power, and the power factor of the distributed generator, a second characteristic line representing a distributed-generator characteristic on the coordinate plane, and estimating the difference between the active power and the reactive power at an intersection point of the first characteristic line and the second characteristic line, and the measured active power and the measured reactive power as the power generation amount of the distributed generator, and output means for outputting power-generation-amount estimation information on the distributed generator estimated by the distributed-generator power-generation-amount estimation means.
Furthermore, a distributed-generator power-generation-amount estimation method for estimating, from active power and reactive power measured at regular intervals by measurement means installed on an electric power system, a power generation amount of a distributed generator interconnected to the electric power system, the distributed-generator power-generation-amount estimation method includes estimating, as a ratio of a time change amount of the active power and the reactive power, a power factor of the distributed generator interconnected to a demand side of the electric power system from a measurement point by the measurement means, and obtaining, from active power and reactive power measured at a time of no power when the distributed generator interconnected to the electric power system is not generating power, a first characteristic line representing a load characteristic on a coordinate plane based on active power and reactive power, obtaining, from the measured active power, the measured reactive power, and the power factor of the distributed generator, a second characteristic line representing a distributed-generator characteristic on the coordinate plane, and estimating the difference between the active power and the reactive power at an intersection point of the first characteristic line and the second characteristic line, and the measured active power and the measured reactive power as the power generation amount of the distributed generator.
Advantageous Effects of Invention
According to the present invention, it is possible to more accurately and easily estimate a power generation amount of a distributed generator DG as compared with a conventional technique.
Thus, according to an embodiment of the present invention, a business entity operating an electric power system can prepare the setting states of the facilities in the electric power system in appropriate states so as to handle any sudden change in the power generation amount of the distributed generator DG at any time. Accordingly, it is possible to increase the interconnection amount of a distributed generator DG to an electric power system, and to improve the electric power quality more than before when the power generation amount of the distributed generator DG suddenly changes.
›BRIEF DESCRIPTION OF DRAWINGS
FIG. 1 is a diagram showing an entire configuration of an area-unit distributed-generator power-generation-amount estimation apparatus.
FIG. 2 is a diagram showing an example of a display screen for inputting handled by an input function I.
FIG. 3 is a diagram showing an example of a display screen for outputting handled by an output function O.
FIG. 4 is a diagram showing an image of processing in a power-factor estimation function C 1 .
FIG. 5 is a flowchart showing a processing procedure of the power-factor estimation function C 1 .
FIG. 6 is a diagram showing table definitions of a tidal-current-measurement-value database DB 1 .
FIG. 7 is a diagram showing an image of processing in an abnormal-value determination function C 2 .
FIG. 8 is a flowchart showing a processing procedure of the abnormal-value determination function C 2 .
FIG. 9 is a diagram showing table definitions of a power-factor-control-information database DB 2 .
FIG. 10 is a diagram showing an image of processing in a power-generation-amount estimation function C 3 .
FIG. 11 is a flowchart showing a processing procedure of the power-generation-amount estimation function C 3 .
FIG. 12 is a diagram showing table definitions of a load-characteristic database DB 3 .
FIG. 13 is a diagram showing an example of data stored in the load-characteristic database DB 3 .
FIG. 14 is a diagram showing table definitions of an estimation-value database DB 4 .
FIG. 15 is a diagram showing an image of processing of a conventional power-generation-amount estimation function.
›DESCRIPTION OF EMBODIMENTS · 1 of 6
An Embodiment of the present invention will be described below with reference to the drawings.
Embodiment
FIG. 1 shows an entire configuration of an area-unit distributed-generator power-generation-amount estimation apparatus. This apparatus is implemented by a general computer including an input function I, an output function O, a calculation function C, and a storage function M. First, the outline of the entire apparatus will be described.
In the input function I, a setting condition used particularly in the calculation function C of the area-unit distributed-generator power-generation-amount estimation apparatus is defined. The input function I includes an estimation-condition input function I 1 , a normal-range input function I 2 , and a date/time designation function I 3 . The estimation-condition input function I 1 is used for inputting a setting condition for estimating a power generation amount of a distributed generator DG. The normal-range input function I 2 is used for determining whether a power-factor estimation value of the distributed generator DG is an abnormal value. The date/time designation function I 3 is used for setting the date and time when data is extracted from a database to verify estimation values of the power factor or the power generation of the distributed generator DG in the past. The input function I will be described later with reference to FIG. 2 .
The output function O includes a power-generation-amount output function O 1 , an estimation-process output function O 2 , a power-factor output function O 3 , and a history output function O 4 . The power-generation-amount output function O 1 is used for outputting an estimation value of the power generation amount of the distributed generator DG. The estimation-process output function O 2 is used for outputting a calculation process of estimating the power generation amount of the distributed generator DG as an image. The power-factor output function O 3 is used for outputting a power-factor estimation value of the distributed generator DG. The history output function O 4 is used for outputting actual data of the estimation values of the power factor and the power generation amount of the distributed generator DG. The output function O will be described later with reference to FIG. 3 .
The storage function M is configured, for example, as a database DB, and includes a tidal-current-measurement-value database DB 1 , a power-factor-control-information database DB 2 , a load-characteristic database DB 3 , and an estimation-value database DB 4 . The tidal-current-measurement-value database DB 1 stores a measurement value D 1 of a tidal current. The power-factor-control-information database DB 2 contains power-factor control information D 2 . The load-characteristic database DB 3 contains load-characteristic data D 3 . The estimation-value database DB 4 stores an estimation value D 4 of a calculation result. The power-factor-control-information database DB 2 stores a power-factor instruction value when a control function (not shown) of the electric power system controls a power factor of the distributed generator DG in real time.
The calculation function C includes a power-factor estimation function C 1 , an abnormal-value determination function C 2 , and a power-generation-amount estimation function C 3 .
The power-factor estimation function C 1 estimates, from the estimation condition received from the estimation-condition input function I 1 and a tidal-current measurement value D 1 (active power and reactive power) measured in the electric power system and stored in the tidal-current-measurement-value database DB 1 , a power factor as a whole including a plurality of distributed generators DG on the downstream of the measurement point of the tidal-current measurement value, and outputs the power factor to the abnormal-value determination function C 2 . When the power generation amount of distributed generators in units of areas is estimated, the tidal-current measurement value D 1 (active power and reactive power) is set as the bank installation position of the substation in the electric power system. The power-factor estimation function C 1 will be described later with reference to FIG. 5 .
The abnormal-value determination function C 2 determines, based on the information on the power-factor normal range input by the normal-range input function I 2 , whether the power-factor estimation value output by the power-factor estimation function C 1 is within the normal range. Incidentally, the power-factor-control-information database DB 2 stores a power-factor instruction value when the control function of the electric power system controls a power factor of the distributed generator DG in real time. When the power-factor control value at the current time is stored in the power-factor-control-information database DB 2 , the abnormal-value determination function C 2 replaces the power-factor estimation value with the power-factor control value, and determines whether the power-factor control value is within the normal range. The power-factor estimation value after the determination is output to the power-generation-amount estimation function C 3 , the power-factor output function O 3 , and the estimation-value database DB 4 . The abnormal-value determination function C 2 will be described later with reference to FIG. 8 .
The power-generation-amount estimation function C 3 estimates, from power-factor information output by the abnormal-value determination function C 2 , load-characteristic information D 3 of the load-characteristic database DB 3 , and tidal-current-measurement-value information D 1 of the tidal-current-measurement-value database DB 1 , the power generation amount (active power and reactive power) of all the distributed generators DG on the downstream of the tidal-current measurement point. The information on the estimated power generation amount is output to the power-generation-amount output function O 1 and the estimation-value database DB 4 . The image of the calculation process is output to an estimation-process output function O 3 so that the operator can visually understand the calculation process in the power-generation-amount estimation function C 3 . The power-generation-amount estimation function C 3 will be described later with reference to FIG. 11 .
›DESCRIPTION OF EMBODIMENTS · 2 of 6
Among the information of the power-factor estimation value and the power-generation estimation value of the distributed generator DG recorded in the estimation-value database DB 4 , the data matching the period output by the date/time designation function I 3 is output to the history output function O 4 .
Hereinafter, the processing of each function will be described in detail.
FIG. 2 is a diagram showing an example of a display screen for inputting handled by the input function I. The input function I includes the estimation-condition input function I 1 , the normal-range input function I 2 , and the date/time designation function I 3 .
The estimation-condition input function I 1 sets a power-generation-amount estimation cycle and a tidal-current-measurement-value interval for estimating a power factor. The power-generation-amount estimation cycle is a function for setting an interval for executing the estimation processing of the power generation amount of the distributed generator DG interconnecting to the electric power system. In this example, it is assumed that the processing is performed at a 10-second cycle. The tidal-current-measurement-value interval for estimating a power factor is a function for setting a time interval of measurement data, which is tidal-current data (active power and reactive power) measured at another time, from which the power factor of the distributed generator DG is estimated. In this example, it is assumed that the processing is performed at a 10-second cycle.
The normal-range input function I 2 designates, as the power-factor estimation value of the distributed generator DG, the normal range in advance. In this example, the normal range is designated as the upper limit of 1.0 and the lower limit of 0.5.
The date/time designation function I 3 is a function for setting, when the operator refers to the actual data of the power-factor estimation value of the distributed generator DG and of the power-generation-amount estimation value of the distributed generator DG, the reference period. In the illustrated example, 30 minutes from 12:00 on Aug. 1, 2015 to 12:30 on the same day are designated as the reference period. In FIG. 2 , the method of inputting the values in the above functions I 1 , I 2 , and I 3 is shown as a pull-down system as an example, but the setting method is not limited to this system.
FIG. 3 is a diagram showing an example of a display screen for outputting handled by the output function O. The output function O includes the power-generation-amount output function O 1 , the estimation-process output function O 2 , the power-factor output function O 3 , and the history output function O 4 .
The power-generation-amount output function O 1 is a function for outputting power-generation-amount prediction values (active power estimation value Kw and reactive power estimation value KVar) of the distributed generator DG output by the power-generation-amount estimation function C 3 as a numerical value or graph.
The estimation-process output function O 2 is a function for visually displaying the process in which the power-generation-amount estimation function C 3 estimates the power generation amount of the distributed generator DG. In the illustrated example, the process is displayed on the coordinate plane based on the active power and the reactive power.
The power-factor output function O 3 is a function for displaying the power-factor estimation value output by the abnormal-value determination function C 2 as a numerical value or graph.
The history output function O 4 is a function for displaying data of a period designated by the date/time designation function I 3 from the past power-factor estimation value of the distributed generator DG and power-generation-amount estimation value of the distributed generator DG that are stored in the estimation-value database DB 4 . In the illustrated example, the active power, the reactive power, and the power factor for 30 minutes from 12:00 on Aug. 1, 2015 to 12:30 on the same day designated by date/time designation function I 3 are displayed as numerical values.
FIG. 4 is a diagram showing an image of processing in the power-factor estimation function C 1 . The upper part of FIG. 4 shows the time-series waveform of the active power measured in the electric power system, and the lower part of FIG. 4 shows the time-series waveform of the reactive power waveform measured at the same measurement point of the electric power system. In this drawing, it is assumed that the active power and the reactive power are measured at intervals of 10 seconds as an example, and the graph shows time-series measured values from 12:00:00 to 12:00:30.
Here, the fluctuation manner of the active power P and the reactive power Q measured in the electric power system is based on that the fluctuation in the load of the consumer interconnected to the system overlaps with the fluctuation in the output of the distributed generator DG. In the present invention, the fluctuation in the active power P and the reactive power Q is caused by that the fluctuation in the load of the customer overlaps with the fluctuation in the output of the distributed generator DG, but that the output of the distributed generator DG generally fluctuates more abruptly than the fluctuation in the load of the consumer is focused on. In other words, if it is limited to a very short time window (several seconds to several tens of seconds), it can be assumed that the change in the load of the consumer is almost 0, and, thus, the change in the active power and the reactive power in this time window is caused by the output of the distributed generator DG. Therefore, by showing the measurement data of 30 seconds from 12:00:00 to 12:00:30 in FIG. 4 , the fluctuation due to the output of the distributed generator DG alone is indicated.
FIG. 4 shows an example in which the active power changes by ΔP and the reactive power changes by ΔQ for the seconds from 12:00:10 to 12:00:20. From the above concept, ΔP and ΔQ can be regarded as the fluctuation amount of the power generation amount of the distributed generator DG. Here, the ratio of the magnitude of ΔP and ΔQ is determined by the power factor as a whole including all the distributed generators DG interconnected to the downstream of the measurement point of the active power and the reactive power. That is, from ΔP and ΔQ, the power factor as a whole can be estimated by Formula (2).
›DESCRIPTION OF EMBODIMENTS · 3 of 6
[Mathematical Formula 2]
Power-factor estimation value=cos(tan −1 (Δ Q/ΔP )) (2)
Where ΔP is the difference in the active power (kW) measured at different times and ΔQ is also the difference in reactive power (kvar). The time intervals for calculating ΔP of the active power and ΔQ of the reactive power are the same, and the timings are also the same. In short, this processing is to determine the power factor from the ratio of the time change amount of the active power and the reactive power.
FIG. 5 is a flowchart showing a processing procedure of the power-factor estimation function C 1 . This flowchart is executed in accordance with an estimated cycle of the power generation amount of the distributed generator DG. The value of the estimated cycle of the power generation amount of the distributed generator DG is the value of the power-generation-amount estimation cycle of the estimation-condition input function I 1 .
In the first processing step S 11 , a tidal-current measurement value at the current time is acquired. In this processing, the measurement values of the active power and the reactive power at the current time are acquired by referring to the tidal-current-measurement-value database DB 1 . FIG. 6 shows table definitions of the tidal-current-measurement-value database DB 1 . The database DB 1 stores the measurement values of the active power and the reactive power corresponding to the date and time in real time.
In the next processing step S 12 in FIG. 5 , the tidal-current-measurement-value interval is acquired. The tidal-current-measurement-value interval is a time width for calculating ΔP and ΔQ later. As the value of the tidal-current-measurement-value interval, the value of the tidal-current-measurement-value interval for estimating a power factor of the estimation-condition input function I 1 is used.
In the processing step S 13 , a past tidal-current measurement value is acquired. Here, the active power and the reactive power at the time going back by the time length acquired in the processing step S 12 from the current time are acquired from the tidal-current-measurement-value database DB 1 .
In the processing step S 14 , the active-power change amount ΔP is calculated. ΔP is calculated by Formula (3).
[Mathematical Formula 3]
Δ P=P t −P t−Δt (3)
Where, P t is the active power at the current time, and P t−Δt is the active power measured at a certain past time.
In the processing step S 15 , the reactive-power change amount ΔQ is calculated. ΔQ is calculated by Formula (4).
[Mathematical Formula 4]
Δ Q=Q t −Q t−Δt (4)
Where, Q t is the reactive power at the current time, and Q t−Δt is the reactive power measured at a certain past time.
The processing step S 16 is a power-factor estimation function. This function calculates the power-factor estimation value using ΔP and ΔQ by Formula (2).
The processing step S 17 is output processing of the power-factor estimation value. In this processing, the power-factor estimation value at the current time determined in the processing steps S 14 , S 15 , and S 16 is output to the abnormal-value determination function C 2 .
In this embodiment, ΔP is compared with the reference value in processing step S 15 , but it is also possible to compare ΔQ with the reference value or to compare both ΔP and ΔQ with the reference value.
FIG. 7 is a diagram showing an image of processing in the abnormal-value determination function C 2 . Here, a graph of the power-factor estimation value corresponding to time is shown. The upper limit value 1.0 and the lower limit value 0.5 of the normal range of the power factor are also indicated. In this drawing, the power-factor estimation value at 10:00:20 departs from the lower limit value of 0.5 of the normal range. Therefore, the function C 2 determines that the power-factor estimation value at that time is an abnormal value.
FIG. 8 is a flowchart showing a processing procedure of the abnormal-value determination function C 2 . This flowchart is executed in accordance with an estimated cycle of the power generation amount of the distributed generator DG. The value of the estimated cycle of the power generation amount of the distributed generator DG is the value of the power-generation-amount estimation cycle of the estimation-condition input function I 1 .
In the first processing step S 21 in FIG. 8 , the upper and lower limit values of the power-factor normal range are acquired. The upper limit value 1.0 and the lower limit value 0.5 of the power-factor normal range are the set values of the normal-range input function I 2 .
In the processing step S 22 , a power-factor estimation value is acquired. The power-factor estimation value is acquired from the power-factor estimation function C 1 .
The processing step S 23 is a branching function for determining whether there is power-factor control information at the current time. The power-factor control information referred in this description is information on the power-factor instruction amount in a case where the control system of the electric power system performs control to intentionally lower the power factor of the distributed generator DG in order to stably supply electric power. The power-factor-control-information database DB 2 is referred to in order to recognize whether there is the power-factor control information, and the magnitude thereof. Here, FIG. 9 shows table definitions of the power-factor-control-information database DB 2 , and that a power-factor instruction value corresponding to the year, month, day and time when the control system in the electric power system has performed power-factor control is recorded. The data at the time when the control system in the electric power system has not performed the power-factor control of the distributed generator DG is not recorded in this table.
In the processing step S 23 , the power-factor-control-information database DB 2 is referred to in order to confirm whether there is power-factor control information at the current time. When there is power-factor control information at the current time, the processing proceeds to the processing step S 24 , and the power-factor estimation value received from the power-factor estimation function C 1 is replaced with the value recorded in the power-factor-control-information database DB 2 . On the other hand, when there is no power factor control information at the current time in the power-factor-control-information database DB 2 , the processing proceeds from the processing step S 23 to the processing step S 25 .
›DESCRIPTION OF EMBODIMENTS · 4 of 6
In the processing step S 25 , it is determined whether the power-factor estimation value is within the normal range. When Formula (5) is satisfied at this function, the power-factor estimation value is determined to be a normal value, or when Formula (5) is not satisfied, the power-factor estimation value is determined to be an abnormal value.
[Mathematical Formula 5]
Lower limit value of power-factor normal range≤power-factor estimation value≤upper limit value of power-factor normal range (5)
Where, the lower limit value and the upper limit value of the power-factor normal range are the setting information of the normal-range input function I 2 . When it is determined that the power-factor estimation value is in the normal range in the processing step S 25 , the processing proceeds to the processing step S 27 . On the other hand, when it is determined that the power-factor estimation value is an abnormal value in the processing step S 25 , “99” is set as the power-factor estimation value in order to indicate that the power factor is an abnormal value in S 26 .
In the processing step S 27 , the processing for outputting the power-factor estimation value is performed. The output destinations of the power-factor estimation value are the power-generation-amount estimation function C 3 , the power-factor output function O 3 , and the estimation-value database DB 4 .
FIG. 10 is a diagram showing an image of processing in the power-generation-amount estimation function C 3 . FIG. 10 shows a coordinate plane based on the active power P and the reactive power Q. In this processing, the power generation amount of all the distributed generators DG interconnected to the downstream of the measurement point of the active power and the reactive power. As an example of the method, first, a load-characteristic line L 1 is drawn on the coordinates of the active power and the reactive power ( FIG. 10 ). The load characteristic referred in this description is the relationship between the active power and the reactive power measured at the previous measurement point when the distributed generator DG is not generating power.
As a technique for obtaining the load-characteristic line L 1 , the technique described in Non-Patent Document 1 can be applied. By putting plots on the PQ coordinate plane according to the active power P and the reactive power Q measured in units of banks of the substation or the like while the distributed generator DG is stopped and by performing, for example, linear approximation processing based on these plots, the load characteristic of the electric power system can be previously specified. This obtaining method is effective when it can be confirmed that the distributed generator DG is stopped.
In contrast, as an actual operation of the electric power system, if the distributed generator DG only includes photovoltaic power generation, it can be determined that the operation is stopped by obtaining nighttime data, but if the distributed generator DG includes wind power generation, it is necessary to separately confirm nighttime and stoppage of the wind power generation.
As a method for obtaining a line L 1 of another load characteristic in consideration of this point, by putting plots on the coordinate plane according to the active power P and the reactive power Q measured in units of banks of the substation or the like in the past without the condition of operation stop, and by performing, for example, linear approximation processing so that the magnitude of the active power P or the reactive power Q is to be maximum in the fourth quadrant (active power P is positive, reactive power Q is negative) in the coordinate plane or in the first quadrant (the active power P and the reactive power Q are positive), the load characteristic of the electric power system can be previously specified.
Next, real-time measurement values of the active power and reactive power are put on the coordinate (indicated as a point N in FIG. 10 ). Furthermore, a line L 2 passing through the point N and having the power factor angle θ of the power-factor estimation value of the distributed generator DG is drawn (here, described as the power-factor characteristic). Then, the intersection point of the load-characteristic line L 1 and the power-factor characteristic line L 2 is set as R.
Considering the relationship between the point N and the point R, the point R corresponds to the active power and reactive power measured at the measurement point when all the distributed generators DG are not generating power at the current time. On the other hand, the point N is a measurement value, including the power generation effect of the distributed generator DG, of the active power and the reactive power. That is, the divergence width between the point N and the point R is the power generation amount of the distributed generator DG. Thus, the active power component of the power generation amount of the distributed generator DG can be calculated as a value P DG obtained by subtracting the active power P L at the point C from the active power P H at the point R. On the other hand, the reactive power component of the power generation amount of the distributed generator DG can be calculated as the value Q DG obtained by subtracting the reactive power Q L at the point R from the reactive power Q H at the point N.
FIG. 11 is a flowchart showing a processing procedure of the power-generation-amount estimation function C 3 . This flowchart is executed in accordance with an estimated cycle of the power generation amount of the distributed generator DG. The value of the estimated cycle of the power generation amount of the distributed generator DG is the value of the power-generation-amount estimation cycle of the estimation-condition input function I 1 .
In the first processing step S 31 in FIG. 11 , load-characteristic information is acquired. A load-characteristic information database DB 3 is referred to in order to acquire the load-characteristic information. FIG. 13 shows an example of data stored in the load-characteristic database DB 3 . Here, the load characteristic is defined by a plurality of coordinate points. FIG. 12 shows table definitions of the load-characteristic database DB 3 . The coordinates (combination of the active power and the reactive power) of the coordinate points defining the load characteristic are recorded. According to FIGS. 12 and 13 , the load-characteristic line L 1 indicating the relationship between the active power P and the reactive power Q measured in units of banks of the substation or the like while the distributed generator DG is stopped is recorded as the values of PQ at a plurality of points.
›DESCRIPTION OF EMBODIMENTS · 5 of 6
In the processing step S 31 , according to the acquired load-characteristic information, the load-characteristic line L 1 is drawn on the active power-reactive power coordinate plane as described in the description of FIG. 10 .
In the processing step S 32 , a measurement value at the current time is acquired. The tidal-current-measurement-value database DB 1 is referred to in order to acquire the tidal-current measurement value (active power and reactive power) at the current time.
In the processing step S 33 , a power-factor estimation value at the current time is acquired. The power-factor estimation value at the current time is acquired from the abnormal-value determination function C 2 .
The processing step S 34 is a branching function for determining whether the power-factor estimation value at the current time is a normal value. That is, when the power-factor estimation value is not “99”, the value is determined to be a normal value, and the processing proceeds to the processing step S 35 . On the other hand, when the power-factor estimation value is “99”, the value is determined to be an abnormal value, and the processing proceeds to the processing step S 38 .
In the processing step S 35 , a power-factor characteristic is generated. As described in the description of FIG. 10 , in addition to putting the real-time tidal-current measurement value acquired in the processing step S 32 on the active power-reactive power coordinate plane created in the processing in the processing step S 31 , a straight line L 2 (power-factor characteristic) passing through the point N of the tidal-current measurement value and having an estimated angle θ of the power factor acquired in the processing step S 33 is generated.
In the processing step S 36 , on the active power-reactive power coordinate plane, the coordinates of the intersection point R of the load-characteristic line L 1 generated in the processing step S 31 and the power-factor characteristic line L 2 passing through the point N of the tidal-current measurement value generated in the processing step S 35 is calculated.
In the processing step S 37 , the total power generation amount of the distributed generator DG at the current time is estimated. The magnitude of the active power of the total power generation amount of the distributed generator DG is calculated by Formula (6), and the magnitude of the reactive power is calculated by Formula (7).
[Mathematical Formula 6]
Active power generation amount of distributed generator DG=P H −P L (6)
[Mathematical Formula 7]
Reactive power generation amount of distributed generator DG=Q H −Q L (7)
Where, P H is the active power component (kW) at the coordinates of the intersection point R of the load-characteristic line L 1 and the power-factor characteristic line L 2 , P L is the active power measurement value (kW) at the current time, Q H is the reactive power measurement value (kval) at the current time, and Q L is the reactive power component (kval) at the coordinates of the intersection point R of the load-characteristic line L 1 and the power-factor characteristic line L 2 .
In the processing step S 38 , since the power-factor estimation value is an abnormal value, the character “*” meaning “unknown” is set as the power generation amount of the distributed generator DG.
In the processing step S 39 , the processing for outputting the power-generation-amount estimation value is performed. The output destinations of the power-generation-amount estimation value are the power-generation-amount output function O 1 and the estimation-value database DB 4 .
In the processing step S 13 , an image of the process of calculating the power-generation-amount estimation value is output. In this processing, an image diagram visualizing the processing from the processing steps S 31 to S 38 (that is, the image of FIG. 10 ) is generated and outputted to the estimation-process output function O 2 . An example of the output to the estimation-process output function O 2 is shown as O 2 in FIG. 3 .
FIG. 14 shows table definitions of the estimation-value database DB 4 . This table stores, for each date and time, the active power component and the reactive power component of the power generation amount of the distributed generator DG, and the power-factor estimation value. From the data recorded in this table, the data corresponding to the period designated by the date/time designation function I 3 is output to the history output function O 4 . Thus, the operator can confirm the validity of the power-generation-amount estimation value of the distributed generator DG in the past.
FIG. 15 is a diagram showing an image of processing of a conventional power-generation-amount estimation function. According to the conventional method, based on the assumption of the power factor 1.0 of the distributed generator DG, the distance from the tidal-current measurement value at the current time (the point N in the drawing) to the intersection point (the point R′ in the drawing) of the load characteristic and a straight line passing through the point N and parallel to the X axis is calculated as the output of the distributed generator DG. Thus, the output estimation value is estimated to be larger than the case of using the method shown in FIG. 10 . That is, there is a problem that an error can be included since the power factor is not taken into consideration.
According to the present invention, by using the method shown in FIG. 10 in which the power factor of the distributed generator DG is taken into consideration, it is possible to reduce an error of the estimated power generation amount of the distributed generator DG as compared with the conventional method. Accordingly, the present invention has an effect that a business entity operating an electric power system can prepare the setting states of the facilities in the electric power system in appropriate states so as to handle any sudden change in the power generation amount of the distributed generator DG at any time. In addition, the present invention has further effects that the interconnecting amount of the distributed generator DG to the electric power system can be increased and that the power quality can be improved when the power generation amount of the distributed generator DG suddenly changes as compared with the conventional case.
›DESCRIPTION OF EMBODIMENTS · 6 of 6
Note that, the present invention is not limited to the above embodiment, and includes various modifications. For example, the above embodiment has been described in detail in order for the present invention to be easily understood, and is not necessarily limited to those having all the described configurations.
›REFERENCE SIGNS LIST
I input function
I 1 designation condition input function
I 2 normal-range input function
I 3 date/time designation input function
C 1 power-factor estimation function
DB 1 tidal-current-measurement-value database
C 2 abnormal-value determination function
DB 2 power-factor-control-information database
C 3 power-generation-amount estimation function
DB 3 load-characteristic database
DB 4 estimation-value database
O output function
O 1 power-generation-amount output function
O 2 estimation-process output function
O 3 power-factor output function
O 4 history output function
Claims as granted
11 claimsLog in to read the claims of this application.
Log in to unlockClassifications
4 codes- G01R21/133
- H02J3/38
- H02J3/00
- H02J3/18
Claim changes
SoonSee which claims were amended, added or cancelled during examination, with every added and removed word marked.
The published claims of this application are not paired with the granted ones in what we hold.
File wrapper
See the full prosecution history — every USPTO and applicant action on this file, in order.
Log in to unlockDocuments
Log in to open the documents of this file: the application as filed, every office action and response, the notice of allowance.
Log in to unlockChain of title
See the full assignment history — every owner this patent has passed through, with recordation dates and reel/frame numbers.
Log in to unlock